Cost Performance Index (CPI):
Represents the amount of work being completed on a project for every unit of cost spent. CPI is computed by Earned Value / Actual Cost . A value of above ONE means that the project is doing well against the budget.
Schedule Performance Index (SPI):
Represents how close actual work is being completed compared to the schedule. SPI is computed by Earned Value / Planned Value. A value of above ONE means that the project is doing well against the schedule.
PV = Planned Completion (%) * BAC
EV = Actual Completion (%) * BAC
CPI = EV/AC
SPI = EV/PV
EV = Earned Value
PV = Planned Value
BAC = Budget at Completion
AC = Actual Cost
Others; are extracted from Logs of Daily Communications and Documentations.
Golden Role:
Always; train yourself to use % to compare whatsoever you say to both what was done and what will be done..
Always; train yourself to use % to compare whatsoever you say to both what was done and what will be done..
سؤال رمضاني مشروعاتي
ReplyDeleteبفرض أنك عقدت النية على ختم القرآن الكريم في شهر رمضان وأتممت اليوم قراءة سورة البقرة
احسب
EV, PV, SP, SV
وما هو الزمن المقدر لانتهاء مشروع الختمة
Bayhas Al Sawady, PfMP, PMP, ACP, PMO-CP
المفروض في ثاني يوم نكون قرأنا جزئين يعني 40 صفحة
PV = 40 يعني
اللي حصل فعلا أننا قرأنا سورة البقرة 45 صفحة
EV = 45 وبالتالي
SV =5
SPI = 1.125
وبالتالي الوقت المقدر لاكمال الختمة، 30 يوم
SPI تقسيم
26.6 يوم
الهدف من التمرين أن تعلم أن ليس بالضرورة
EV
أن تكون فقط $$