PMgmt is a wonderful "Tango..."




1-      If the increase in one quantity, leads to an increase in other, then the variation is
(Direct proportion)
 
2-      If the increase in one quantity, leads to a decrease in other, then the quantities are in
(Inverse proportion)
 
3-      Arrange the following in the correct order of steps in the project management life cycle. 1. Design, 2. Marketing, 3. Analysis and evaluation 4. Inspection, testing, and delivery
(D)
a.       3, 2, 1, 4
b.       2, 3, 1, 4
c.       4, 3, 2, 1
d.       1, 2, 3, 4
 
4-      when to conduct value engineering
(D)
a.       material prices increase.
b.       Specs are higher/ lower than required.
c.       Cost is over budget.
d.       All the above.
 
5-      Value engineering is done so that the cost is reduced while quality remains within the acceptable limit.
(
Yes)
 
6-      What is most important when closing the project.  
(B)
a.       Cost.
b.       Budget.
c.       Performance
 
7-      Developing new technology is an example of – project, process,
(Project Performance)
 
8-      When to prepare the cost estimate – design stage, concept stage, tender stage, final design stage.
(Launched at initiation, updated thorough all stages up to close out)
 
9-      When to prepare the BOQ - design, concept design, tender design, final design stage.
(Ditto, but usually done at Tender Stage)
 
10-   When to submit material for DM approval – design, concept, construction, final design.?
(At all stages, or as per TOR)
 
11-   What is the scope of consultant in project design?
(All)
a.       Detail drawing.
b.       Design document and project discerption.
c.       Tender document.
 
12-   Steel drawing showing the detail and dimensions of the elements used for construction is called,
(A)
a.       Shop drawings.
b.       Design drawings.
c.       Detailed drawings.
 
13-   Cost control in project management is processed in,
(A, but C is more comprehensive)
a.       Cost control management
b.       Configuration management
c.       Cost control+ configuration management